A construction daily report is a one-page record of what happened on the job today: who was on site and for how long, what got done, what was delivered, what held you up, and anything that went wrong. Fill it out before you leave the site, not on Thursday. Download the free one-page template as a PDF or Excel file below.

Download the template

One page, letter size. Print a stack for the clipboard in the truck, or fill in the Excel file on a laptop. No email, no signup.

construction daily report template, one page

This isn't a four-page superintendent form. It's one sheet a foreman on a small crew will actually fill out in the truck before he heads home, with the crew's hours right up front.

What goes in a construction daily report

Here's every box on the template, in the order it appears:

  1. Job and date. Job name and address, the date, the foreman's name, and a report number so the sheets stay in order.
  2. Weather. Morning and afternoon conditions and the temperature. Short, but it matters when you're pouring concrete, laying block or on a roof.
  3. Crew on site. For each guy: name, trade or role, W-2 or 1099, start, end, lunch, and hours. This is the box that settles "who was there and how long" later. Lunch is a column on this paper form.
  4. Work completed today. Plain bullets by area. "East wall, courses 4 to 9" beats a paragraph.
  5. Deliveries and materials. What showed up, what was short, and who signed for it.
  6. Equipment. What was on site, and what's rented, so the rental doesn't sit there a week nobody's using it.
  7. Visitors and inspections. Who came by, which inspection, pass or fail.
  8. Delays and issues. Weather, waiting on another trade, missing material, a change the customer asked for.
  9. Safety, incidents and near misses. What happened, who got hurt if anyone, and who you told.
  10. Photos. Yes or no, and what of. Photos beat paragraphs.
  11. Signature. The foreman signs. Add the owner's or GC's signature if the job calls for it.

Example: a filled-in day

Here's what a good one looks like. This is a made-up masonry day, just for the example:

  • Job: Hillside Rd. retaining wall · Date: Tue, Oct 13 · Foreman: Mike · Report # 7
  • Weather: AM clear, 52°F. PM cloudy, 61°F.

Crew:

NameRoleW-2 / 1099StartEndLunchHours
MikeForeman / masonW-27:003:3030 min8.0
DaveMasonW-27:003:3030 min8.0
LuisLaborerW-27:003:3030 min8.0
TonySub (pump)109910:001:00none3.0

The lunch column is on this paper form. The example hours already subtract that lunch.

  • Work completed: East section, block courses 4 through 9. Drainage pipe set behind lower courses.
  • Deliveries: Block arrived 9:40, scheduled for 7:30. 2 pallets short. Mike signed with a note.
  • Equipment: Mixer (ours). Mini-excavator (rented, returned 2:00).
  • Visitors and inspections: None.
  • Delays: Crew stacked and staged for two hours waiting on block. Shifted to pipe and backfill prep.
  • Safety: Near miss. A pallet shifted on the forks during unloading. Nobody hurt. Talked to the driver and the crew at lunch.
  • Photos: Yes. Wall progress, short delivery ticket.
  • Signed: Mike

That's it. Ten minutes in the truck, and anybody who asks about Tuesday a month from now gets a straight answer.

Daily report vs time card vs daily log

A daily report, or daily log, is the job's day: what happened on site. A time card is each guy's hours. On big jobs those are different people's paperwork. On a small crew, the foreman usually does both, which is why this template keeps a crew-hours box on the daily report.

If you need the weekly hours for each guy on one sheet, grab the construction timesheet template. If your cards are in hours and minutes, this chart helps you convert minutes to decimal hours.

Tips that keep it from turning into paperwork nobody reads

  • Fill it out before you leave the site. Tomorrow morning, you'll forget the delivery time. By Thursday, you'll forget the whole day.
  • Keep it to one page. If it takes 30 minutes, it won't get done.
  • Take photos. A picture of the short delivery ticket says more than three sentences.
  • Keep a copy with the job file. It's useful if there's a disagreement later about what happened that day.

If hours keep going missing between the job and the office, here's how contractors track crew hours without the Thursday rebuild.

Where My Guys Time fits

If the crew-hours box is the part you're always chasing, that's what My Guys Time does. Each guy joins the crew team from his own phone, he or the foreman logs the hours daily in the browser, the foreman approves the week and adds incident notes on the day something goes wrong, and receipt photos ride on the card. W-2 guys and 1099 subs sit on the same board. $12/month flat for the whole company.

To be straight with you: it's a time card, not a full daily-report app. It doesn't do weather, deliveries or job logs. Keep using this template for that. More on construction time tracking for small crews.

Construction daily reports: common questions

What should be included in a construction daily report?+

The job and date, weather, who was on site and their hours, work completed, deliveries, equipment, visitors and inspections, delays, safety incidents and near misses, photos, and the foreman's signature. Keep each one short.

Who fills out the daily report?+

Usually the foreman or lead on site, before the crew leaves for the day.

Is there a free app for construction daily reports?+

Several construction apps include daily logs. This template costs nothing and works on paper or in Excel. My Guys Time covers crew hours, foreman approval, incident notes and receipt photos for $12/month flat for the whole company, but it isn't a daily-report app.

Daily report vs daily log: what's the difference?+

Mostly the name. Some GCs call the superintendent's own record the "daily log" and the version that goes to the customer the "daily report." For a small crew, one sheet does both jobs.

Do I need a daily report on small residential jobs?+

That depends on your contract and the job, so we can't give a legal answer. Plenty of owners keep one anyway, because it settles "what happened that day" questions fast.